Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harvil Road
- Worksite Name
- Copthall
- Contractor
- SCS JV
- Type of works
- Road closure, Road realignment
- Estimated Start Date
- 12/06/2023
- Estimated End Date
- 10/07/2023
What we are doing
What we are doing
From 12 June to 10 July 2023, we will be carrying out utility works and construction activities to build the northern section of the Harvil Road realignment. To carry out the works safely, we will need to close Harvil Road between Skip Lane and the Dogs Trust for 24 hours a day.
The construction activities that need to be completed during the closure include:
• Diversion of existing utilities
• Existing road demolition
• Highway & drainage construction
• Resurfacing, white lining and installation of street furniture
Please see the following pages for more information about the works we will be carrying out and a map showing the location of the road closure and the diversion route.
How this work might affect you
During the road closure, local access to residential and commercial properties (including the Dogs Trust) will be maintained, however, there will be no through access for emergency services.
A clearly signed diversion route will be in place via Moorhall Road / A412 / A40.
We would like to apologise in advance for any disruption or inconvenience the road closure may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We expect to have completed the realignment of Harvil Road in autumn this year.
Download information relating to these works