Notice of installation of welfare units at Atlas Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-10-16/02/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- SCS JV
- Type of works
- Worksite / compound set-up
- Estimated Start Date
- 22/02/2021
- Estimated End Date
- 12/04/2021
What we are doing
As part of our ongoing works to set up the Atlas Road site, we have been building the foundations for our welfare units, which will provide the site office and facilities for between 200 and 300 staff. We plan to start installation from week commencing 22 February 2021 for up to seven weeks. The work will take place during our working hours of 8am to 6pm, Mondays to Fridays and 8am to 1pm, Saturdays if required.