Notice of intrusive ground investigation surveys on land off Yarnfield Lane

Work item: HS2-HS2-UT-TEM-000-000022 P01

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire, West Midlands
Location
Yarnfield Lane
Worksite Name
Yarnfield Lane
Contractor
National Grid
Type of works
Borehole works, Trial Pits
Estimated Start Date
16/10/2023
Estimated End Date
27/10/2023

What we are doing

In order to construct the railway it is necessary to commission a new National Grid substation. To connect the new substation to the existing electricity network new 33,000volt cables need to be installed.

National Grid need to install a new cable circuit from a connection position at Meaford Substation to the new substation location in land off Yarnfield Lane in Stone, Staffordshire.
One of National Grids framework contractors will carry out initial ground investigation surveys on the land where the proposed substation is to be built.

From Monday the 16th October 2023, four boreholes and two trial pits will be drilled and excavated, samples will be taken and stored in a small compound from where they will be collected for laboratory testing. The site will be fenced and secured for the duration of the works.