Notice of lane and footway closures, A41 – updated

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-45-16/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A41, Waddesdon
Contractor
EKFB JV
Type of works
Footpath closures, Lane closure, Traffic management
Estimated Start Date
03/06/2024
Estimated End Date
22/07/2024

What we are doing

Please see below updated information for the works which commenced in June.

We will be continuing preparatory works ahead of our upcoming realignment of the A41. These works relate to utility connections around the points at which the new road will join the existing A41.

Along the A41 between Waddesdon and the Blackgrove Road/Waddesdon Hill Junction, there will be a lane closure managed by 2-way temporary traffic lights to enable gas and telecoms connections.

During this period the pedestrian footway on the verge will also be closed.
To reduce impact on road users, these traffic lights will be in operation at off-peak times and access will be maintained for residents along the A41.

When will these works take place?

  • Monday 3 June to Friday 22 July – lane closure managed by 2-way traffic lights from 9am-3pm with the exception of 11-14 July and 21 July when both lanes will be open
  • Monday 3 June to Friday 22 July – footway closure, 24 hour

* These works were originally scheduled to be completed on Monday 24 June but have been delayed.