Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Waddesdon
- Contractor
- EKFB JV
- Type of works
- Lane closure, Traffic management, Utility works / surveys
- Estimated Start Date
- 09/05/2024
- Estimated End Date
- 10/04/2024
What we are doing
In preparation for our A41 realignment works, we will be undertaking utility works to allow BT to connect communication cables between two chambers on the A41, near Waddesdon.
As we are working around the carriageway, these works will necessitate a lane closure with traffic management. There will be 4-way traffic lights along the A41 and at the junctions of Blackgrove Road and Waddesdon Hill.
To reduce impact on road users, the traffic lights will be in operation at off-peak hours and access will be maintained for residents along the A41.
When will these works take place?
- Thursday 9 May 9am – 3pm
Every effort will be made to complete these works within one daytime closure.
However, we have planned contingency dates if the works are not completed on 9 May for the following date:
- Friday 10 May 9am – 3pm
These dates are subject to change due to ground conditions but will be completed in or around the anticipated time schedules.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]