Work item: HS2-EW-SCS-Ph1-Ar-So-S1-traf-04/03/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Adelaide Road
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Concrete pours, Road closure
Estimated Start Date
21/03/2024
Estimated End Date
22/03/2024

What we are doing

From 6am to 6pm on Thursday 21 March, there will be a lane closure on Adelaide Road, as concrete will be poured to construct the base slab for the future headhouse.

The closed lane will be used to accommodate a concrete pump, specifically the M36 model, which is too large to fit within our construction site.