Notice of lane closure, Rocky Lane

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-6-01/09/2023 1MC12-EKF-IN-NTE-CS03- 000063

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Rocky Lane
Contractor
EKFB JV
Type of works
Lane closure
Estimated Start Date
21/08/2023
Estimated End Date
25/08/2023

What we are doing

To allow us to complete the water supply connection to our Rocky Lane compound, we need to conclude the final stage of the works to the existing Thames Water main beneath Rocky Lane. To ensure these works are completed safely, we will need to implement a single lane closure for approximately 5 days. Which will be in place 24 hours day between Monday 21 August to  Friday 25 August.