Notice of M42 M6 eastbound link road and M42 southbound traffic management, near Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-11-21/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Coleshill
Worksite Name
M42 M6 eastbound link road, M42 southbound
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
10/10/2022
Estimated End Date
31/03/2023

What we are doing

We will be installing traffic management on both the M42 southbound and M42 M6 link road eastbound from Monday 10 October.
The traffic management along the M42 will be a hard shoulder closure along a short section of the southbound carriageway. This traffic management will be in place 24 hours a day from Monday 10 October until Friday 31 March. This will allow us to safely remove the embankment adjacent to the highway for the future M42 Coleshill Box Structure, that spans across the M42.

The traffic management along the M42 M6 link road will be an overnight eastbound closure. There will be a diversion route in place as part of this overnight closure. (See location of closure and diversion on page 2). This closure will be in place for one night on Monday 10 October, from 9.00pm until 5.00am. This will allow us to safely install of temporary vehicle barrier system.