Updated notice of M42 M6 westbound link road overnight closures

Work item: HS2-MW-BBV-Ph1-Ar-N1-GI-2-14/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Coleshill
Contractor
BBV JV
Type of works
Utility works / surveys
Estimated Start Date
21/11/2022
Estimated End Date
22/11/2022

What we are doing

Updated Notice

We previously sent out a notification outlining overnight closures along the M42 M6 link road westbound on Monday 3 October, Monday 31 October and Thursday 24 November. This was to complete drainage works. Due to unforeseen circumstances, we will now not close the M42 M6 link road westbound on Monday 31 October.
However, to continue our works for the M42 M6 Link Viaduct, we will install two additional nights of closures along the M42 M6 link road westbound. These closures will enable us to safely switch our existing traffic management from a lane 1 closure to a lane 2 closure. The two nights of closures will be Monday 21 November and Tuesday 22 November, from 9.00pm until 5.00am, each night. This work is subject to consent.
Throughout the road closure, a clear diversion route will be installed along the M42 southbound to junction 6, where road users will be able to take a U-turn to re-join the M42 northbound and exit at M42 junction 7 to join the M6 northbound

 