Notice of micro-tunnelling works on Wormwood Scrubs

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-Prog-works-13-10/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Wormwood Scrubs
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Tunnelling
Estimated Start Date
18/04/2022
Estimated End Date
02/05/2022

What we are doing

Wormwood Scrubs micro-tunnelling

A 1.2 m pipe will need to be installed as part of Stamford Brook Sewer diversion to allow for building the Station Box foundations. The location of works is shown on the image overleaf.

To complete this work, we will be using micro-tunnelling. Micro-tunnelling is a digging technique used to construct small tunnels. This work will be completed by using a tunnel boring machine, which will be installed in Wormwood Scrubs and will be driven towards the Station Box on the Old Oak Common Station site. Only a single micro-tunnel will be installed in this part of the Scrubs. This work is needed to allow us to divert the Stamford Brook Sewer.

For safety reasons, the micro-tunnelling works will be 24/7 whilst the tunnels are under construction. This is to avoid the tunnel boring machine being stuck in the ground and causing potential settlement on the surface.

 

 

 