View route map
Notice of mobilisation of worksite at Coleshill Heath Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-50-27/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull, West Midlands
- Location
- Chelmsley Wood
- Worksite Name
- Coleshill Heath Road
- Contractor
- BBV JV
- Type of works
- Delivery of materials, Worksite / compound set-up
- Estimated Start Date
- 15/08/2022
- Estimated End Date
- 14/08/2026
What we are doing
We will soon be mobilising our work site to the north side of Coleshill Heath Road adjacent to Yorkminster Drive. This site will start receiving deliveries of stone and other construction materials. Vehicles will be moving in and out of our site and shaping the materials to form piling platforms. There will also be welfare facilities on site for our workforce. We will start using this site from Monday 15 August and it will remain in use while we build the new railway. Our normal working hours are 8am to 6pm Monday to Friday, and 8am to 1pm on Saturday’s.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]