Notice of obstruction on Clayton Road footpath, Hanchurch Interchange, Update October 2022

Work item: HS2-EW-BB-Ph2a-Ar-CA01-Traf-4-05/10/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Clayton Road, Hanchurch Interchange
Worksite Name
Hanchurch Interchange
Contractor
Balfour Beatty
Type of works
Excavation works, Utility works / surveys
Estimated Start Date
19/10/2022
Estimated End Date
19/10/2022

What we are doing

HS2 Ltd is proposing to make changes to the Hanchurch Interchange at J15 of the M6, Newcastle Road, Clayton Road and the junction of Newcastle, Trentham and Whitmore Road, to improve the traffic flows during the construction of HS2.

During some recent surveys, a piece of equipment became lodged inside a manhole chamber we needed to plan for the safe removal of the equipment

To undertake this work, we need to excavate, by hand, in an area known to contain historic building rubble. As a precaution our operatives will have some additional personal protection equipment (PPE), including dust masks.

When the work will take place

Monday 7 November 2022

from 8am to 4pm