Skip to main page content
View route map

Notice of overnight A38 southbound closures between Hilliard’s Cross and Streethay

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-15-28/07/2023

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire
Location
Streethay
Contractor
BBV JV
Type of works
Overnight road closure, Utility works / surveys
Estimated Start Date
23/08/2023
Estimated End Date
04/09/2023

What we are doing

We are working with South Staffordshire Water who will be undertaking a water main diversion along the A38 at Streethay. To complete these works safely we will install a safety barrier along a section of the southbound carriageway of the A38.

We will have two overnight closures of the A38 southbound carriageway between Hilliard’s Cross and Streethay.
• To install the safety barrier, we will have an overnight closure on Wednesday 23 August 2023 from 9pm to 5am.
• We will remove the safety barrier during an overnight closure on Sunday 3 September 2023 from 9pm to 5am.
A clearly signed diversion route will be in place during the closures.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]