Notice of overnight closure of the westbound carriageway of the M42/M6 Link Road

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-8-03/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
M42/M6 link road
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
23/05/2024
Estimated End Date
24/05/2024

What we are doing

To continue our works in the area, we will be closing the westbound carriageway of the M42/M6 link road. The closure is to facilitate crane access to the central reservation to complete construction activities associated with the permanent bridge bearings.

To ensure the safety of the road users and our workforce, we will install an overnight closure of the westbound carriageway of the link road from 9pm on 23 May, re-opening at 5am on 24 May.

See map below detailing the westbound carriageway closure and the approved diversion route. The diversion route will be to continue on M42 southbound from junction 8 to junction 6. At M42 junction 6 exit the M42 southbound onto the roundabout and take the M42 slip road to go northbound.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]