Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Water Orton, Watton Lane
- Worksite Name
- B4117
- Contractor
- BBV JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 04/04/2022
- Estimated End Date
- 10/04/2022
What we are doing
Subject to consents, BBV will complete ground investigation works in
areas of Watton Lane, near the A446. Our working hours will be from
9.00pm – 5.00am each night. These works will take place over 6 nights,
from Monday 4 April until Saturday 9 April, with the final closure being
removed at 5.00am on Sunday 10 April.
In order for us to carry out these works safely we will install a temporary
overnight closure on Watton Lane throughout the time of the works.
There will be a diversion in place throughout the overnight closures.