Notice of overnight closures of the M42 northbound carriageway
Work item: HS2-BBV-26-1625
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- M42
- Contractor
- BBV JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 30/01/2026
- Estimated End Date
- 30/01/2026
What we are doing
Location
M42 northbound carriageway, between junction 6 and junction 9.
What3Words- from ///supporter.area.loaded to ///humid.finest.them
Duration
One overnight closure from 9pm to 5am, Friday 30 January 2026
What we are doing
We will be conducting motorway and carriageway repairs, in addition to the daily mitigation measures we already have in place.
What to expect
Low level of noise from our machinery and a clearly signed diversion route.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.