Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Survey
- Estimated Start Date
- 14/11/2022
- Estimated End Date
- 18/11/2022
What we are doing
The work we will be completing
To inform our design of the future HS2 railway, we need to carry out surveys in the area. These surveys will include taking core samples from various carriageways, CCTV drainage surveys and trial holes. This work is to check connections between the gullies and manholes. To conduct our surveys safely, we will have temporary traffic measures in place, including a diversion route.