View route map
Notice of overnight hoarding installation at South Ruislip vent shaft site
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Prog-works-47-16/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- South Ruislip
- Contractor
- SCS JV
- Type of works
- Hoarding works
- Estimated Start Date
- 27/06/2021
- Estimated End Date
- 11/07/2021
What we are doing
What we are doing
From 27 June to 11 July 2021, we will be installing 3.6m high hoarding overnight around the perimeter of our site to maintain a safe and secure environment for site personnel.
This work will be outside of core working hours Monday to Saturday 10pm to 5.30am.
How the work might affect you
The team will require lighting overnight and noise will be minimal as we fix the hoarding into position.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]