Notice of overnight lane and road closure A413 London Road, Wendover

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-11-15/06/2023 1MC12-EKF-IN-NTE-CS03-000087

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Contractor
EKFB JV
Type of works
Overnight road closure, Traffic management
Estimated Start Date
20/11/2023
Estimated End Date
13/01/2024

What we are doing

To enable the next phase of construction of the Small Dean Viaduct we will be undertaking a small realignment of the A413 London Road. Once the road has been temporarily realignment it will enable us to continue with the construction of two of the viaduct piers.

There will be three phases of construction coming up that will have short duration impacts on the road from October into December. All works are taking place overnight to reduce their impact on road users and once complete the temporary new realignment will be in operation, an image of the Phase 1 temporary diversion is included in the attachment.

  • Overnight lane closure for excavation and installation of drainage
  • Overnight lane closure to complete remaining excavation and install kerb tie-ins.
  • Overnight full closure for surfacing tie-ins and tarmacking

When will these works take place?

Overnight lane closures with traffic lights:

  • Monday 20 November to Saturday 25 November (8:30pm to  5:30am)
  • Monday 27 November – Saturday 2 December (8.30pm to 5.30am)

Overnight full road closure:

  • Monday 11 December to Saturday 16 December (8:30pm to 5:30am)
  • Monday 18 December – Thursday 21 December (8.30pm to 5.30am)
  • Monday 8 January to Saturday 13 January (8.30pm to 5.30am)

To minimise disruption, we will introduce a fully signposted diversion route and have chosen to work overnight to reduce our road impact.

These dates may be subject to change due to circumstances outside of our control.