Notice of overnight lane and road closures A413 London Road, Wendover (updated Jan 2024)
Work item: 1MC12-EKF-IN-NTE-CS03-000097
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Contractor
- EKFB JV
- Type of works
- Lane closure, Road closure, Road realignment
- Estimated Start Date
- 08/01/2024
- Estimated End Date
- 27/01/2024
What we are doing
To enable the next phase of construction of the Small Dean Viaduct we will be undertaking a small realignment of the A413 London Road. Once the road has been temporarily realigned it will enable us to continue with the construction of two of the viaduct piers.
There will be various phases of construction coming up that will have short duration impacts on the road from through to February 2024. All works are taking place overnight to reduce their impact on road users and once complete the temporary new realignment will be in operation.
Please see the notification in the link showing the temporary diversion.|
The phases of works are as follows:
- Overnight lane closure for excavation and installation of drainage
- Overnight lane closure to install kerb tie-ins
- Overnight full closure for surfacing tie-ins and tarmacking
When will these works take place?
Overnight lane closures with traffic lights:
- Monday 8 January to Saturday 13 January (8.30pm to 5.30am)
Overnight full road closure:
- Monday 15 January to Saturday 20 January (8.30pm to 5.30am)
- Monday 22 January to Saturday 27 January (8.30pm to 5.30am)
To minimise disruption, we will introduce a fully signposted diversion route and have chosen to work overnight to reduce our road impact.
These dates may be subject to change due to circumstances outside of our control.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]