Notice of overnight rail works – (Saturdays) near Millburn Grange Farm, Kenilworth

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-5-07/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Kenilworth
Contractor
BBV JV
Type of works
Survey
Estimated Start Date
17/07/2021
Estimated End Date
04/12/2021

What we are doing

BBV will be carrying out track monitoring and other survey works including cable route surveys of the existing Network Rail equipment on the Leamington Spa to Coventry rail line. This is to allow for monitoring of rail equipment before and during construction works for HS2 and to identify existing cables within the Network Rail boundaries.

The survey and monitoring works are scheduled for the following Saturday nights: 17 July, 14 August, 11 September, 9 October, 16 October, 23 October, 30 October, 6 November and 4 December 2021. These works will finish 8:30am Sunday mornings. These works are non-intrusive with only very low levels of noise being generated.