Notice of overnight road closure A413 London Road, Wendover

Work item: 1MC12-EKF-IN-NTE-CS03-000110 HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-01-12/02/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Contractor
EKFB JV
Type of works
Overnight road closure
Estimated Start Date
26/02/2024
Estimated End Date
02/04/2024

What we are doing

As we move to the next phase of construction of the Small Dean Viaduct, we need to close the A413, London Road, to safely carry out construction of the viaduct piers.

During this time, we will be working on excavation work to construct the piers, and construction of a sheet pile wall.

When will these works take place?

Overnight full road closure (8.30pm to 5.30am):

  • Monday 26 February to Saturday 2 March
  • Monday 4 March to Saturday 9 March
  • Friday 29 March to Tuesday 2 April

Every effort will be made to complete these works within three overnight closures.

However, we have planned the below contingency dates if the works can’t be completed due to circumstances outside of our control, such as adverse weather.

  • Monday 11 to Tuesday 19 March

To minimise disruption, we will introduce a fully signposted diversion route and have chosen to work overnight during full closures, to reduce our road impact.

These dates may be subject to change due to circumstances outside of our control but works will be completed in or around the set timeframes.