Notice of overnight road closures A413, London Road, Small Dean
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-35-18/10/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Worksite Name
- A413 Small Dean
- Contractor
- EKFB JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 05/11/2024
- Estimated End Date
- 13/12/2024
What we are doing
We will be undertaking multiple works at the Small Dean viaduct to prepare for the viaduct launch in early 2025. We will complete trial holes in the verge of the road and commence the lifting of hammerhead units for the construction of the final pier. As we need to protect the safety of our team working close to the carriageway, the A413, London Road will be closed for the duration of our works.
Update for December closures
We will need to extend the overnight road closures into December to install a new barrier that meets the curvature of the road.
For the dates and map of the work location please see the notification below.
For more information on the construction of Small Dean viaduct please see this video:
Small Dean Viaduct crossing over 413 – YouTube
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]