Notice of overnight road closures, A43, Brackley BP roundabout to the Syresham junction
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-39-08/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Worksite Name
- A43
- Contractor
- EKFB JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 07/08/2023
- Estimated End Date
- 13/10/2023
What we are doing
During the construction of the temporary diversion on the A43, there will be some localised vegetation clearance as well as installing drainage underneath the road.
The A43 southbound will be closed overnight Mon-Fri between 8pm and 6am: Monday 2 October to Friday 6 October and on Monday 9 October.
The A43 northbound will be closed overnight Mon-Fri between 8pm and 6am : Tuesday 10 October to Friday 13 October
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]