Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-39-08/07/2023

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Worksite Name
A43
Contractor
EKFB JV
Type of works
Overnight road closure
Estimated Start Date
07/08/2023
Estimated End Date
13/10/2023

What we are doing

During the construction of the temporary diversion on the A43, there will be some localised vegetation clearance as well as installing drainage underneath the road.

The A43 southbound will be closed overnight Mon-Fri between 8pm and 6am: Monday 2 October to Friday 6 October and on Monday 9 October.

The A43 northbound will be closed overnight Mon-Fri between 8pm and 6am : Tuesday 10 October to Friday 13 October

 