Notice of overnight road closures, A43, Brackley BP roundabout to the Syresham junction
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-7-28/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire, Oxfordshire
- Location
- A43
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 11/03/2024
- Estimated End Date
- 15/03/2024
What we are doing
Earlier this year we began constructing a temporary diversion of a short section of the A43 in both directions, running alongside the existing A43, near Brackley. This diversion is required so that we can build the new A43 Overbridge that will carry traffic over the HS2 railway line. We are now ready to complete further utility diversions, including the installation of pipework and manholes as well as temporary earthworks. These works are for the centre island site of the new A43 Overbridge.
The A43 Southbound will be fully closed overnight, from the Syresham Junction to the Brackley BP roundabout, Mon-Fri from 8pm to 6am, on the following dates:
• Monday 11 March to Friday 15 March
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]