Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-7-28/09/2023

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire, Oxfordshire
Location
A43
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
11/03/2024
Estimated End Date
15/03/2024

What we are doing

Earlier this year we began constructing a temporary diversion of a short section of the A43 in both directions, running alongside the existing A43, near Brackley. This diversion is required so that we can build the new A43 Overbridge that will carry traffic over the HS2 railway line. We are now ready to complete further utility diversions, including the installation of pipework and manholes as well as temporary earthworks. These works are for the centre island site of the new A43 Overbridge.

The A43 Southbound will be fully closed overnight, from the Syresham Junction to the Brackley BP roundabout, Mon-Fri from 8pm to 6am, on the following dates:
• Monday 11 March to Friday 15 March

 