UPDATED Notice of overnight road closures and daytime lane closures, A413 London Road, Wendover
Work item: HS2-EKFB-25-1044
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Worksite Name
- A413
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 06/05/2025
- Estimated End Date
- 27/05/2025
What we are doing
In May to June, we will be continuing with construction at the Small Dean Viaduct. This will involve lifting precast concrete segments, pouring the bottom slab of the viaduct.
To prevent the risk of concrete dripping onto the road, onto the A413, there will be overnight closures of the road to complete these works safely.
Overnight road closures (8:30pm – 5:30am):
- Tuesday 6 May – Friday 9 May
- Wednesday 18 June – Saturday 21 June
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]