Notice of overnight single lane closures on the M42
Work item: HS2-MW-LM-Ph1-Ar-No-N1-Traf-8-03/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Bickenhill
- Contractor
- LM JV
- Type of works
- Traffic management
- Estimated Start Date
- 15/03/2021
- Estimated End Date
- 27/03/2021
What we are doing
We’re improving the local road network
When the future HS2 Interchange Station is operational, four new highways bridges will connect the current road network to new routes we are creating. The first of these new highways bridges was safely installed in August 2020 over the M42, and the second was installed in October 2020 over the A446. This year, we’ll carry out various activities to fully reinstate these roads such as street lighting connections.
We’ll be starting work on Monday 15 March
To carry out this work safely, we will install:
• Temporary overnight single lane closures along the M42 southbound from 10pm to 5am, between Monday 15 March and Saturday 27 March (see map on page 2)
Signed diversion routes will be in place for drivers during the overnight road closures. Our contractors may be on site up to an hour before and after these times to set up and close down the site.