Work item: HS2-MW-UT-Ph1-Ar-So-S1-UT-22-04/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
01/03/2021
Estimated End Date
02/03/2021

What we are doing

Overnight surveys on 30 and 31 March 2021
We will be carrying out drainage surveys on Horsenden Lane on 30 and 31 March. The surveys will take place overnight in three phases between 9pm and 6am.
The surveys will help us to investigate the condition of the drainage system and consider the best way to protect the system while we build HS2. We may need to flush the drains using a high-pressure water jet. Your utility services will not be affected during these works.

Temporary changes on Horsenden Lane South
A partial lane closure and temporary traffic lights will be in place overnight on Horsenden Lane South near the junction with Selbourne Gardens. Access to this area will not be affected.
We will require a suspension of parking bays on Horsenden Lane and Bus Stops G and PF will be closed overnight on the above dates. A map showing the location of the surveys and temporary changes is shown on pages 2 and 3.

Dates may change due to unforeseen circumstances. We will continue to provide updates about our works at HS2inKilburn-Northolt.co.uk