View route map
Notice of overnight traffic management, A413 Wendover Bypass
Work item: HS2-EKFB-25-1201
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Worksite Name
- Wendover Bypass
- Contractor
- EKFB JV
- Type of works
- Traffic management
- Estimated Start Date
- 22/08/2025
- Estimated End Date
- 23/08/2025
What we are doing
In Autumn 2025, we will be constructing a new entrance from the Wendover Bypass for site vehicles to enter the Wendover green tunnel compound.
Prior to the construction of the entrance, we are required to complete a survey of the road. In order to complete the survey safely, there will be a lane closure of the northbound lane with two-way traffic management.
To reduce impact on road users, this traffic management will be in operation at off-peak times.
The works will take place Friday 22 August (8:30pm) – Saturday 23 August 2025 (5:30am)
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]