Notice of overnight traffic management A453 Sutton Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-05-14/05/2024
Work Item Summary
- Region
- Staffordshire, West Midlands
- Location
- Bangley
- Contractor
- Balfour Beatty
- Type of works
- Traffic management
- Estimated Start Date
- 13/08/2024
- Estimated End Date
- 14/08/2024
What we are doing
We recently created a temporary diversion on the A453 Sutton Road; to allow for future construction works, this will enable the new railway to pass underneath A453 Sutton Road. The new temporary diversion will minimise impact on the road during construction.
To enable us to complete these works we will require temporary overnight traffic management on A453 to complete installation of permanent traffic signage and to conduct surveys.
To minimise disruption, the work will take place overnight. We will have temporary traffic lights in place between 8pm and 6am from 13 August until 14 August 2024. Due to the nature of our works these lights may be moved along the road to ensure a safe working area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]