UPDATE: Notice of overnight week night closures of the M42/ M6 Link Road, near Water Orton
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-39-20/11/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- M42
- Worksite Name
- M42
- Contractor
- BBV JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 31/01/2025
- Estimated End Date
- 19/12/2025
What we are doing
The work scheduled to begin in January 2025 will mark the next phase of the M42/ M6 Link road viaduct project. Our teams will install the parapets on the East viaduct bridge and remove equipment from the previous phase of construction. The work we will be undertaking involves delivering plant and machinery and extra carriageway cleaning operations. This cleaning programme will be in addition to the daily mitigation measures we have in place and will ensure that impact from our work to the motorway link is reduced as much as possible.
To ensure the safety of the road users and our workforce, we will install overnight closures of the eastbound and westbound carriageways on the M42/M6 link road from 9pm each night and re-opening at 5am each morning. See below a breakdown of these overnight closures from January to December 2025. M42/M6 Westbound • Thursday 30 January • Thursday 27 February • Thursday 27 March • Thursday 24 April • Thursday 29 May • Thursday 26 June • Thursday 24 July • Thursday 28 August • Thursday 25 September • Thursday 30 October • Thursday 27 November • Thursday 18 December This work is subject to consent with National Highways.
UPDATE: The traffic management on Friday 25 July has been cancelled.