Notice of part-closure of footpath on Eastside City Park

Work item: HS2-MW-MD-Ph1-Bir-Cur-St-N4-Prog-works-36-21/03/202

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Curzon Street
Worksite Name
Park Street
Contractor
Mace Dragados JV
Type of works
Electrical Works
Estimated Start Date
09/06/2025
Estimated End Date
10/08/2025

What we are doing

Update: we will complete work at this location by early-August.

National Grid need to divert power cables on the junction of Park Street and Eastside City Park. This is to provide the main electricity supply to the Curzon Street station site.

During these works, we need to reduce the width of the footpath on Eastside City Park, near the pedestrian traffic lights on Park Street/Masshouse Circus. This is for the safety of pedestrians and our workforce.

We will separate the footpath with barriers and place signs advising pedestrians and cyclists that the footpath is open during these works.

The maps below show the work areas for National Grid, during this work we will also replace some of our hoardings to CLD fencing on Eastside City Park.

We plan to start work between Monday, 9 to Friday, 27 June. It will take approximately three weeks to complete.

Update – the utility works have taken longer than anticipated and will be complete in early-Jul.