Notice of part-closure of footpath on Eastside City Park
Work item: HS2-MW-MD-Ph1-Bir-Cur-St-N4-Prog-works-36-21/03/202
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Curzon Street
- Worksite Name
- Park Street
- Contractor
- Mace Dragados JV
- Type of works
- Electrical Works
- Estimated Start Date
- 09/06/2025
- Estimated End Date
- 10/08/2025
What we are doing
Update: we will complete work at this location by early-August.
National Grid need to divert power cables on the junction of Park Street and Eastside City Park. This is to provide the main electricity supply to the Curzon Street station site.
During these works, we need to reduce the width of the footpath on Eastside City Park, near the pedestrian traffic lights on Park Street/Masshouse Circus. This is for the safety of pedestrians and our workforce.
We will separate the footpath with barriers and place signs advising pedestrians and cyclists that the footpath is open during these works.
The maps below show the work areas for National Grid, during this work we will also replace some of our hoardings to CLD fencing on Eastside City Park.
We plan to start work between Monday, 9 to Friday, 27 June. It will take approximately three weeks to complete.
Update – the utility works have taken longer than anticipated and will be complete in early-Jul.