Notice of partial road closure on A47 Heartlands Parkway
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-30-17/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- A47, Aston Church Road
- Worksite Name
- A47 Heartlands Parkway, Aston Church Road
- Contractor
- BBV JV
- Type of works
- Partial Road Closure, Road closure
- Estimated Start Date
- 12/04/2025
- Estimated End Date
- 13/04/2025
What we are doing
Constructing a new Aston Church Road Overbridge
As we build the new high speed railway line in Birmingham, we need to rebuild the existing overbridge on Aston Church Road. We need to do this work because the existing bridge does not currently have enough headroom for the new HS2 trains to pass underneath. To rebuild the bridge, we currently have Aston Church Road closed to all vehicles.
Partial Road Closure
As part of the Aston Church Road closure works, we will also need to close a section of A47 Heartlands Parkway on Saturday 12 April and Sunday 13 April from 8.00pm to 6.00am. See map overleaf for details.
Diversion route
To keep traffic moving in the area cars will be diverted along A47 Heartlands Parkway, Saltley Viaduct and Washwood Heath Road. Access to businesses and properties will be maintained.