Notice of piling works at Atlas Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-41-16/03/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 30/03/2021
- Estimated End Date
- 31/07/2021
What we are doing
From 30 March until 31 July 2021, we will be carrying out piling works in our Atlas Road site. The piling works are needed to build the tunnel launch box and ramp that will allow for construction of the Atlas Road logistics tunnel using a tunnel boring machine (TBM). The dates for these works are subject to approval with Network Rail. We will let you know if the dates change.