Update: Notice of piling works – Curzon Street Station site

Work item: HS2-MW-MD-Ph1-Bir-Cur-St-N4-OTH-49-15/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Birmingham, Curzon Street
Worksite Name
Curzon Station
Contractor
Mace Dragados JV
Type of works
Piling
Estimated Start Date
05/02/2024
Estimated End Date
15/03/2024

What we are doing

In preparation for the construction of HS2’s Curzon Street Station and the railway, Mace Dragados (MDJV) have been working with Network Rail to plan piling works. These works will support the retaining wall on the West Coast main railway lines.

Most of the work will be carried out during our core working hours Monday to Friday, 8.00 am to 6.00 pm.

We have six piles to construct that are very close to Network Rail overhead equipment, for safety reasons, we cannot construct these piles when trains are in service.  In collaboration with Network Rail, we have planned to carry out these works over four weekends at night-time. Network Rail will suspend trains during these nighttime works to allow our workforce to operate safely.

The dates for the works have been revised.  Please download the information relating to these works document below.  

Download information relating to these works