Notice of piling works – Duddeston Mill Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-46-14/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Saltley
- Worksite Name
- Duddeston Mill Road
- Contractor
- BBV JV
- Type of works
- Piling
- Estimated Start Date
- 03/01/2023
- Estimated End Date
- 03/02/2023
What we are doing
Piling works
As we continue construction of the new Duddeston Mill Road Underbridge, we will need to install bored piles into the ground to create the foundations for the piers of the bridge.
This new 21.5-meter bridge will carry two Network Rail lines over Duddeston Mill Road. These two lines are currently located on the existing Duddeston Mill bridge but will need to be removed to make space for the pier of the new Duddeston Junction Viaduct which will carry the HS2 line.
We plan to carry out these piling works on the north side of Duddeston Mill Road from Tuesday 3 January until Friday 3 February.
Pedestrian management
As we carry out this work, we will need to lift materials at various points. To keep pedestrians safe, they may experience delays of passage on the footpath of up to five minutes as materials are lifted overhead.