Tower cranes removal from Camden Cutting south
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-15/06/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden
- Worksite Name
- Camden Cutting south
- Contractor
- SCS JV
- Type of works
- Construction, Crane removal
- Estimated Start Date
- 04/07/2023
- Estimated End Date
- 16/07/2023
What we are doing
From 4 to 16 July we will remove two tower cranes from our Camden Cutting south worksite, via our site access on Hampstead Road. We will work from 8am to 8pm to deconstruct the cranes and remove them from our worksite in sections. For safety, due to the size of the cranes, they can only be transported early in the morning or late at night when there is less traffic on the road. The cranes will be removed from site between 8pm and 10pm.
We expect it will take about two days to remove each crane. We plan to take down the cranes on 4 , 5, 13 and 14 July. Depending on the weather forecast, we may need to work on 6, 7, 15 and 16 July instead.
We do not expect these works to be noisy.
Further details of above works and other ongoing weekend works are in the notification below.