Notice of piling works near the A38 northbound at Streethay
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-03-09/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire, West Midlands
- Location
- Streethay
- Contractor
- BBV JV
- Type of works
- Piling
- Estimated Start Date
- 29/02/2024
- Estimated End Date
- 15/05/2024
What we are doing
We will begin piling works on land near to the A38 northbound. These works will enable us to begin the construction of the new HS2 line to pass underneath the A38. Piling involves driving deep, strong columns into the ground to provide a solid base for our future structures.
The piling works will begin on 29 February and will be carried out in two phases:
Phase One
From the 29 February until 4 April 2024, our working hours will be from 8am until 10pm. Our work will be carried out Monday to Friday.
This will include an additional two-hour shut down period, each night.
Phase Two
From the 18 March until 15 May 2024, we will have a second team on site. Working hours for this section of work will be 8am until 6pm Monday to Friday.
Should we need to carry out any maintenance work this will be done on the weekends. From 1pm until 6pm on Saturday and 10am until 5pm on Sunday
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]