Notice of pipeline diversion works near Rookery Lane, Hints
Work item: HS2-EW-UT-Ph1-Ar-No-N1-UT-42-03/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire, West Midlands
- Location
- Hints
- Contractor
- Cadent Gas
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 01/03/2021
- Estimated End Date
- 22/03/2021
What we are doing
What are we doing?
Before we start the main work to move the pipeline, we need to carry out some preparation works on Land north of Rookery Lane. We will be carrying out preparation works for around three weeks from the beginning of March 2021.
The works involve:
• Removal of some vegetation on land north of Rookery Lane. Appropriate ecological surveys will be undertaken before any vegetation
clearance. Our ecologist will be present throughout the activity to ensure there is no disruption to local wildlife.
• Creating a site access at the private lane off Watling street. So that we can avoid the use of School Lane and Rookery Lane, we’ll be
constructing a bridge across Black Brook and laying track mat across the fields that vehicles will use to reach our working area at Rookery Lane. We will also be using temporary traffic lights on a section of Watling Street so we can create our site access safely. This has been discussed and agreed with Staffordshire County Council.
We will keep local people up to date as we progress to main diversion works.
How will this affect you?
We will only need to the temporary traffic lights occasionally and, wherever possible, outside of peak traffic times. Signs will be in place to make road users aware. Standard vehicles and equipment will be used, and we do not anticipate the works will cause disruption to local people.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]