Skip to main page content
View route map

Notice of planned utility works on Kilburn High Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-09/04/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Kilburn
Worksite Name
Kilburn
Contractor
SCS JV
Estimated Start Date
13/05/2024
Estimated End Date
30/08/2024

What we are doing

We will be carrying out works to protect and upgrade the main gas pipe below the lower end of Kilburn High Road between Greville Road and Oxford Road. We will be digging a number of trenches along the road to reach the depth of the main gas pipe. The existing metal gas pipe will be replaced with polyethylene (plastic).

 

These works are scheduled to take place from 13 May until 30 August 2024.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]