Notice of precast delivery, Chipping Warden
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-48-23/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Chipping Warden
- Contractor
- EKFB JV
- Type of works
- Tunnel segment delivery
- Estimated Start Date
- 20/08/2023
- Estimated End Date
- 03/09/2023
What we are doing
In Chipping Warden, we are constructing the Chipping Warden Green Tunnel. We will soon be receiving the delivery of a particularly wide precast tunnel segment. This segment, which includes some additional design features, will require a lane
closure for the safety of road users. To safely deliver this abnormal load, the southbound carriageway of the A361 will be closed off-peak, for a short period between 5am and 9am, on Sunday 20 August 2023, with a back up date of 3 September 2023.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]