Notice of preparatory works in Waddesdon ahead of main construction
Work item: 1MC12-EKF-IN-NTE-CS08-000001
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Waddesdon
- Contractor
- Fusion JV
- Type of works
- Archaeology, Environmental mitigation works
- Estimated Start Date
- 06/07/2020
- Estimated End Date
- 31/05/2021
What we are doing
In preparation for our main works to start, we are undertaking the following works during 2020:
- temporary compound
- ecological surveys
- species translocation
- vegetation clearance
- fencing
- ecology site maintenance
- archaeology
To enable us to complete all the works detailed above we will have set up two small temporary site compounds. The primary access to the site will be from the A41, Blackgrove Road. The secondary access will be from the A41, Station Road leading to Quainton Road.
Each compound site will have 24/7 security, welfare units, storage facilities, temporary lighting and car parking for the workforce.
To access across the fields temporary metal trackway will be laid for vehicle access.
For further information about the works in the area please view or download our works update newsletter below.