View route map
Notice of public right of way diversion in Wendover, Ellesborough Road South Field
Work item: HS2-MW-Fusion -Ph1-Ar-Ce-C2-OTH-48-02/06/2021 FUS_AWN_0176
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Wendover
- Contractor
- Fusion JV
- Type of works
- Early construction works, Works affecting Public Rights of Way
- Estimated Start Date
- 22/02/2021
- Estimated End Date
- 15/03/2021
What we are doing
As part of our continuing work ahead of the construction of the railway we need to undertake some further activity in your area. This will consist of:
- Utility surveys
- Preparation works
- Boundary fencing
- Public right of way diversion
When will these works take place?
These works are planned to start on 22 February 2021 and are expected to take two weeks to complete. The site for the fencing works is located between Ellesborough Road and Bacombe Lane. Access to the site will be from Bacombe Lane.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]