Notice of public right of way diversion in Wendover, Ellesborough Road South Field

Work item: HS2-MW-Fusion -Ph1-Ar-Ce-C2-OTH-48-02/06/2021 FUS_AWN_0176

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Wendover
Contractor
Fusion JV
Type of works
Early construction works, Works affecting Public Rights of Way
Estimated Start Date
22/02/2021
Estimated End Date
15/03/2021

What we are doing

As part of our continuing work ahead of the construction of the railway we need to undertake some further activity in your area. This will consist of:

  • Utility surveys
  • Preparation works
  • Boundary fencing
  • Public right of way diversion

When will these works take place?

These works are planned to start on 22 February 2021 and are expected to take two weeks to complete. The site for the fencing works is located between Ellesborough Road and Bacombe Lane. Access to the site will be from Bacombe Lane.