Notice of Public Right of Way upgrades, Calvert
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-02-05/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire, Oxfordshire, South East
- Contractor
- EKFB JV
- Type of works
- Works affecting Public Rights of Way
- Estimated Start Date
- 24/03/2025
- Estimated End Date
- 11/04/2025
What we are doing
As part of the HS2 works, we are required to upgrade the local following Public Rights of Way (PRoW);
• GUN/24/1
• GUN/23/1
• EDG/12/1
• CAG/1/1
• CAG/4/3
• CAG/5/1
The above PRoW’s will be closed from 24 March until 11 April 2025
for planned upgrade works to be completed.