Notice of Public Rights of Way Closure, Wendover
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-15-06/12/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Contractor
- EKFB JV
- Type of works
- Footpath closures
- Estimated Start Date
- 27/01/2025
- Estimated End Date
- 29/01/2025
What we are doing
In January, we will be undertaking trial hole works in the north of Wendover, around the Dobbins Lane and Bridleways area. The works are required in order to locate utility services prior to the second phase of the spring chamber work in the farm area behind Dobbins Lane. To complete these works safely, we will be required to narrow the road between Dobbins Lane and Bridleways. There will also be a footpath closure of WEN10/1.
From: Monday 27 January – Thursday 30 January 2025
Download information relating to these works
Find out more about