Notice of Public Rights of Way (PRoW) diversion W129d and W130, Cubbington

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-43-16/08/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Cubbington
Contractor
BBV JV
Type of works
Works affecting Public Rights of Way
Estimated Start Date
10/11/2023
Estimated End Date
31/12/2024

What we are doing

To facilitate the project delivery work and to ensure user safety, we will be diverting W129d and W130. The diversion will be in place from 4 June 2022 until 31 December 2024.
Pedestrians will still be able to safely navigate through the area by using the clearly signposted diverted footpath as illustrated in the map on the notification.

Download information relating to these works