Notice of remaining works for electricity pylon diversion scheme, Colne Valley

Work item: HS2-EW-NG-Ph1-Ar-Ce-C1-Prog-Works-01-18/08/2023-02/April 2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Colne Valley
Contractor
National Grid
Type of works
Bridge works
Estimated Start Date
02/04/2024
Estimated End Date
30/06/2024

What we are doing

In Spring 2024 National Grid will remove the remaining temporary bridge over the River Colne and associated infrastructure that’s been in place for its HS2 pylon diversion scheme. Reinstatement of the area will follow.

When the work will take place
Our contractor, Morrisons, will start the work 2 April 2024. It will take two and a half months to complete.

There may be some low-level noise, but we don’t expect any disruption to residents.

None of the work will affect electricity supplies.