Notice of remedial works, gas pipeline diversion at Pipe Ridware

Work item: HS2-MW-UT-Ph2A-Prog-works-45-12/03/2024

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Pipe Wood Lane
Worksite Name
Pipe Ridware
Contractor
National Gas
Type of works
Gas Main Works
Estimated Start Date
07/05/2024
Estimated End Date
11/05/2024

What we are doing

National Gas need to relocate two gas pipeline test posts in fields near Pipe Wood Lane. This is so the pipeline can be accessed in the future for testing, maintenance and monitoring purposes. The relocation is essential for the recently diverted pipeline undertaken at this location due to HS2 works. They’ll excavate two 20-30 metre trenches to the fence line, lay cables and relocate the test posts.

Our contractor, United Living, will start the work on 7th May 2024.  We expect the work to take 4-5 days.

None of the work will affect gas supplies.