Notice of road closure, A41
Work item: 1MC12-EKF-IN-NTE-CS04-000078 HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-02-09/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A41
- Contractor
- EKFB JV
- Type of works
- Overnight road closure, Utility works / surveys
- Estimated Start Date
- 15/03/2024
- Estimated End Date
- 17/03/2024
What we are doing
In preparation for our A41 realignment works, we will be undertaking utility works to protect cabling by installing ducts on the A41, near Waddesdon.
This ducting will enable the diversion of the BT cable on Blackgrove Road. The work will involve cutting a trench in the carriageway, followed by reinstatement.
As we are working around the carriageway, two consecutive overnight road closures will be in place for road users.
Access to properties along the A41 will be maintained.
When will these works take place?
- Friday 15 into Saturday 16 March and Saturday 16 into Sunday 17 March between 8:30pm – 5:30am
Every effort will be made to complete these works within two overnight closures.
However, we have planned contingency dates the following weekend if the works can’t be completed due to circumstances outside of our control, such as adverse weather.
- Overnight on Friday 22 into Saturday 23 March and Saturday 23 into Sunday 24 March between 8:30pm – 5:30am (contingency dates)
These dates are subject to change due to ground conditions but will be completed in or around the anticipated time schedules.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]