Notice of road closure, A41

Work item: 1MC12-EKF-IN-NTE-CS04-000078 HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-02-09/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A41
Contractor
EKFB JV
Type of works
Overnight road closure, Utility works / surveys
Estimated Start Date
15/03/2024
Estimated End Date
17/03/2024

What we are doing

In preparation for our A41 realignment works, we will be undertaking utility works to protect cabling by installing ducts on the A41, near Waddesdon.

This ducting will enable the diversion of the BT cable on Blackgrove Road. The work will involve cutting a trench in the carriageway, followed by reinstatement.

As we are working around the carriageway, two consecutive overnight road closures will be in place for road users.

Access to properties along the A41 will be maintained.

When will these works take place?

  • Friday 15 into Saturday 16 March and Saturday 16 into Sunday 17 March between 8:30pm – 5:30am

Every effort will be made to complete these works within two overnight closures.

However, we have planned contingency dates the following weekend if the works can’t be completed due to circumstances outside of our control, such as adverse weather.

  • Overnight on Friday 22 into Saturday 23 March and Saturday 23 into Sunday 24 March between 8:30pm – 5:30am (contingency dates)

These dates are subject to change due to ground conditions but will be completed in or around the anticipated time schedules.