Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-10-05/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Kenilworth
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
16/09/2024
Estimated End Date
25/10/2024

What we are doing

Construction Update
In July we shared information about the forthcoming closure of the A429 Kenilworth Road from Monday 2 September to Sunday 29 September. As we have continued to develop our programme we have identified the need to undertake further inspections and surveys of drainage and utilities, as well as verge maintenance, ahead of the planned closure. To do this safely manned stop-go boards will be used.

Phase one: Monday 16 September – Friday 27 September
Stop-go boards will be operated as required during off peak hours between 9.30am to 3.30pm Monday to Friday only.
We will be undertaking further surveys and verge maintenance.

Phase two: Monday 30 September – Friday 25 October
A 24/7 full road closure of A429 Kenilworth Road will be in place for four weeks. A fully signposted diversion will be in place.
We will be undertaking the relocation of utilities to the new road alignment and completing earthworks to build the embankments.
Access for pedestrians and cyclists will be maintained.

Phase three: Early 2025
We will install another full road closure to complete the permanent road realignment. Details will be shared early next year.

Join us for a community drop-in event in Kenilworth on Tuesday 24 September to find out more about the A429 and next phase of A46 works. Please see more details on page three of the notification.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]